Water System Project Status Report

February 27th, 2025

Leave a reply »

Gala Water System Project

The water system project in this community started last February 3, 2025 by construction of catchment impounding box from the water source. Then it was followed by construction of a concrete drive tank. On the same day, the stainless impounding tank including the plastic hose was delivered in the area.

To date, the digging, hauling and lay-outing of black hoses is being done.

Cadmang and Baculi Water System

The stainless tank for the two areas was delivered last February 4, 2025. It was followed by the delivery of plastic hose upon completion of its production last February 21, 2025.

Up to the moment, the materials is ongoing delivery to the site to where the project will be established. In Baculi area, the construction of catchment impounding box from the source was started as per reported by the Chieftain (IPMR) of the community who is also the oversight project holder but need for further validation to be done this week. Both work on water system project in this community is ongoing.

END.